Building Construction Update:              November 2017:

 The K-12 construction project continues to be on-time for occupancy over the holiday break which is scheduled to begin on Monday December 18.  When students return on January 8th 2018, they will be reporting to the new building.

Close-out activities in the new building include:

  • Interior door hardware installation
  • Exterior door installation has been completed
  • Installation of technology core and racks
  • Carpet and vinyl floor installation in classrooms
  • Finish application to the wooden gym floors
  • Sealer application to the terrazzo flooring
  • Installation of classroom and office furnishings
  • Installation of landscape mulch and plants
  • Installation of the playground equipment and play surface
  • Install of a temporary walkway between existing building and new building entrance to facilitate the moving process.
  • Continued planning for the moving of the pre-school classes to the Victory Chapel Church until renovation is completed in the 1998portion of the varsity gymnasium
  • HVAC system is inspected, tested and fully operational

 

**We plan to provide students with a building tour and orientation prior to holiday break, as well as having students move their personal belongings to the new building the week prior to holiday vacations alleviating the need to return to the old building after the break.